4000629011
Your position:Home > News >

American standard plug valve installation and maintenance

date:2021-01-07 09:38
When installing the American standard plug valve, in order to prevent damage to the plug valve and ensure the full performance of the plug valve, the following four points should be paid attention to:   
1. Make sure the valve is open.  Heat the pipe first.  Transfer as much heat as possible from the pipe to the plug valve.  Avoid extending the heating time of the plug valve itself.
2. Use gauze or steel wire brush to remove the pipe and cutting parts to make the metal surface shiny.  It is recommended not to use steel wool.
3. First cut the pipe in the vertical direction, trim and remove burrs, and measure the pipe diameter.
4. Apply flux to the outside of the pipe and the inside of the welding cover. The flux must completely cover the welding surface.  Please use flux sparingly

 

Masonillan (Shanghai) Control System Co., Ltd. is a wholly-owned enterprise of the American Masoneilan Group.

CONTACT US

A19, 6F, Block b, No. 1539, Zhongxing Road, Jingan District, Shanghai

Hot-Line: 400-0629-011

E-mail: sale@masoneilangroup.com

给您供应:梅索尼兰阀门,进口阀门,梅索尼兰控制阀,梅索尼兰定位器控制阀等多品类产品
为您提供阀门选型,安装介绍,产品详细参数,行情走势等信息。
Copyright Masonillan ALL Rights Reserved 备案号:沪ICP备2020035224号-2